Employee Philosophy  
Mechanical Electrical Lighting Technology Sustainable Design Building Commissioning
Hospitality Commercial Recreation Public Healthcare Educational Residential Lighting Design Sustainable Design
Beaudin Ganze Consulting Engineers Dobson Penrose Electrical Penrose Mechanical Summit Sundeck Wagner Park Christiania  
Conferences Seminars Press Releases  
Beaudin Ganze Consulting Engineers
Return to Home Page About Us Expertise Experience Awards News and Publications Recruiting Search Our Site Contact Us
Beaudin Ganze
Beaudin Ganze Consulting Engineers
Penrose Mechanical Awards :: Beaudin Ganze Consulting Engineers
Consulting Engineers
Change your text size. Change your text size to small Change your text size to medium Change your text size to large Change your text size to largest Change your text size/

Penrose HospitalPenrose Mechanical
Beaudin Ganze Consulting Engineers

ACEC Colorado 1995 Merit Award

A CRISIS IN COMFORT

Colorado Springs, Colorado

Take a hospital’s campus chilled water system . . .

The Penrose Hospital campus in Colorado Springs, Colorado, was 836,000 square feet and growing. As the premier health care provider in the Pikes Peak region of the Rocky Mountains, patient expectations for quality health care were high.

The core of the facility’s comfort control system, the central chilled water system, was not getting the cooling job done. Patients were uncomfortable, bed counts were dropping, and the engineering department was continually attempting to address the problem: a costly chiller addition was being considered.

. . . and make it work!

Beaudin Ganze Consulting Engineers

THE ENGINEERING CHALLENGE CROSSED TECHNICAL, COMMERCIAL, ENVIRONMENTAL, AND SOCIAL BOUNDARIES:

  • System problems were identified. New solutions had to be developed at the most innovative level. The traditional remedy of adding more pumps only made matters worse. Adding another large central chiller looked like the answer.
  • The complexity of finding and solving the system distribution problems was amplified by the requirement to simultaneously upgrade the central chiller plant refrigerant detection system.
  • The solutions had to be affordable and implemented with minimal disruption in patient care.
  • In addition to increasing the patients’ comfort level, the general public should benefit from the environmentally safe solutions.
  • State-of-the-art technology was to be superseded by “Future-of-the-art” technology at every opportunity.

Beaudin Ganze Consulting Engineers

GOOD, OLD-FASHIONED HARD WORK was required to map the entire chilled water system, which serves nine major buildings. Partnering with the mechanical contractors and facility team leaders was paramount to identify system problems, which others had failed to observe.

OPEN BYPASS PIPING WAS DISCOVERED IN THE BASEMENT OF THE 14-STORY PATIENT TOWER: Differential pressure was not available to deliver chilled water up through the tower. The original solution, implemented years earlier to boost the flow up the tower, was failing.

RETURN SIDE PRESSURES, WHEN BOOSTED BY COIL PUMPS, BECAME HIGHER THAN DOWNSTREAM SUPPLY SIDE PRESSURES: Downstream cooling coils were experiencing reverse water flow and an unacceptable rise in discharge air temperature.

COOLING COILS WERE PIPED BACKWARDS: A 20% loss in cooling effectiveness was experienced.

INNOVATIVE SOLUTIONS for the chilled water distribution problems were implemented: the anticipated approach of installing another chiller was not going to solve the problems. Calculations had shown the existing central plant, at 2,200 tons of cooling capacity, was large enough to handle the campus load of 1,875 tons. The solutions were simple.

VALVES WERE INSTALLED IN THE SYSTEM BYPASSES and closed, which caused differential pressures to improve dramatically (from zero to 25 psi minimum): flow was achieved to the tower.

BOOSTER PUMPS WERE REMOVED: Reverse flows were eliminated.

COIL PIPING WAS CORRECTED: Discharge air temperatures dropped from 80°F to 56°F.

WHILE THE BEAUTY OF THE SOLUTIONS

. . . lay in their SIMPLICITY, implementing them was extremely COMPLEX. Piping problems were found in all of the buildings. However, the major bypasses that had to be closed were located in the basement of the 14-story patient tower, where the chilled water for all floors was piped.

Disruptions in patient care on all floors had to be kept to a minimum. An eight-phase plan was developed and implemented to sequence the piping changes as quickly as possible with minimal hospital disturbance.

RIGID TIME AND BUDGET CONSTRAINTS

. . . were imposed on the project and were met. Upfront savings were realized on the expected cost: $750,000 had been budgeted for the anticipated new chiller and pumps (the traditional remedy), while only $250,000 was spent. Anticipated annual energy savings were calculated to be $75,500. This exceeded the owner’s requirements for a successful project.

THE GENERAL PUBLIC BENEFITS, as well as the patients, from these solutions: the chilled water distribution system uses less energy to deliver more cooling in a manner that is environmentally safer.

Chilled water can now be distributed as needed. Patient complaints have reduced dramatically. Excess series booster pumping was eliminated. Correctly directed flow to cooling coils through the use of primary-secondary piping has reduced energy costs. A Direct Digital Control System controls both the chiller plant and a new refrigerant detection system. The future chilled water needs of the facility can now be readily incorporated into this highly efficient system.

THE HOSPITAL IS THE EMBODIMENT OF SOLUTIONS FOR THE FUTURE: use a thorough investigation to diagnose the problems . . . THEN TREAT THE DISEASE, NOT THE SYMPTOMS.

 

A “FUTURE-OF-THE-ART” dual refrigerant monitoring and detection system was installed in the central chiller plant. An environmentally safer refrigerant, R123, replaced F11 (an ozone depleting refrigerant) to upgrade one of the central electric chillers. By meeting the requirements of anticipated extensive FUTURE mechanical codes TODAY, the system leads the NATION in the design of refrigeration machinery rooms.

“With the cooperative team effort of engineers, mechanical contractors and facilities team leaders, the project exceeded all expectations. Even though the very complex nature of this job required numerous phased shutdowns for system drain downs, it was completed within a few months’ time.”

“The project was on time, under budget, and will result in significant ongoing savings.”

David Howard
Director, Facilities

 

Consulting Engineers